‘Delivering Homes, Building Communities’ Through Offsite and Other Modern Methods of Construction

‘Delivering Homes, Building Communities’ Through Offsite and Other Modern Methods of Construction

‘Delivering Homes, Building Communities’ Through Offsite and Other Modern Methods of Construction MMC

 

MMC to mitigate the State’s development delivery risk

 

Ireland’s new housing strategy treats MMC as a core national delivery system, not a technology category. Following extensive multidisciplinary sessions of knowledge and insights exchange with industry, the State is now reorganising procurement, finance, skills, regulation, and design to force a shift from traditional construction to industrialised delivery.

 

Breakdown of what changes – and why it matters

 

  1. Mandatory MMC Use in Public Delivery (for the first time)

The plan requires:

  • 25% of all new social and affordable homes to be delivered using MMC
  • Applies across local authorities, AHBs and LDA programmes
  • Embedded in funding conditions, meaning any LA/partner seeking capital must demonstrate MMC integration

 

This creates a predictable, State-backed MMC workload measured in thousands of units, not dozens.

 

  1. Policy Driven by Quantified Performance Gains

Government has formally adopted MMC because empirical outputs outperform traditional building:

  • Up to 40% shorter site programmes
  • Reduced design variation for fewer site-stage RFIs
  • Cleaner sequencing for lower cost overruns
  • Factory production for lower waste and more predictable embodied carbon
  • Reduced dependence on trades currently in structural undersupply

 

This is now written into the State’s justification for investment – MMC is seen not as innovation, but as risk mitigation.

 

  1. Volumetric Systems Are Being Directly Funded and Tested at Scale

Two fully funded pathfinder programmes test volumetric delivery in real conditions:

 

Limerick SMART Homes Project

  • Short-term modular affordable rental transition model
  • State-supported under MMC innovation funding
  • Designed to validate deployability, cost profile and tenant acceptance

Wexford – Cluain Fada (22 permanent homes)

  • Fully 3D volumetric delivery
  • Using a Design and Build contract to streamline procurement
  • Contract award targeted for end of 2025

 

This signals Government’s intent to accelerate toward full-volumetric systems, not just panelised manufacturing.

 

  1. Standardisation Moves from Recommendation to Requirement

The biggest structural move is the State mandating one design language for public housing:

  • Mandatory use of:
    • Design Manual for Quality Housing
    • Employer’s Requirements for Detail Design of Quality Housing
  • New Standardised Design Approaches publication outlines:
    • approved MMC-compatible typologies
    • repeatable details
    • standardised layouts
    • standard spans, modules and wall build-ups

 

This reduces:

  • design cost duplication
  • factory retooling
  • planning-stage redesign
  • procurement delays caused by non-standard specs

 

It creates conditions for mass customisation rather than bespoke design, which is essential for MMC facility viability.

 

  1. Certification Reform Goes After the Slowest Part of MMC Adoption

NSAI Agrément certification has been the major layout-time bottleneck for MMC. The plan now includes:

  • Expanded NSAI MMC Agrément team (already underway)
  • A new MMC Agrément Toolkit with technical guidance for offsite manufacturers
  • A Government-commissioned root-cause analysis on certification delays (first time this has been done)
  • Work on a new Irish Standard for light-gauge steel, mirroring existing timber-frame standards

 

This will shorten the time required for new systems to reach the market – historically 12–24 months for some suppliers.

 

  1. Skills Strategy Built Explicitly Around Offsite Delivery

Government accepts the workforce requirement difference:

  • 69,000 new workers required with MMC adoption
  • 79,000 under traditional-only construction
  • The 10,000-worker gap and the productivity benefit MMC provides

 

To support this:

  • A new MMC traineeship (specialist offsite manufacturing pipeline)
  • MMC training for senior LA staff and industry leadership
  • MMC-specific modules added to the National Construction Training Campus
  • Apprenticeships increasing from 9,000 to 12,500 per year by 2030
  • A new National Framework for Meeting Priority Construction Workforce Needs aligned to offsite

 

*Critically, skills development is now a factory-first model, not a site-first one.

 

  1. Finance Structure Rebuilt to Match MMC’s Cost Curve

The plan accepts the economic reality of MMC: capital is required upfront, not in linear drawdowns.

 

Government interventions:

  • ISIF-backed funds will proactively target MMC factory investment
  • Enterprise Ireland doubling its Built to Innovate investment (already €6.5m)
  • EI will now provide:
    • technical support for certification preparation
    • R&D supports
    • lean-manufacturing transformation programmes
    • financial leadership mentorship for MMC SMEs

These changes make it possible for MMC manufacturers to scale without relying solely on developer-by-developer orders.

 

  1. Integrating SMEs into MMC (Not Replacing Them)

Given that 97% of Irish construction firms employ fewer than 10 people, the State is intentionally avoiding a “factory-only oligopoly”.

 

Specific mechanisms:

  • LDA regional MMC pipeline will include SME builders
  • Requirement for large developers to mentor SMEs on MMC delivery
  • Lean Construction processes being rolled out across residential delivery
  • Procurement changes (below) will explicitly favour SME participation

 

This acknowledges that rural and regional delivery cannot be centralised in a handful of factories.

 

  1. Procurement Reform – Now With Real Structural Detail

Instead of generic “simplification”, the new national procurement strategy includes precise mechanisms that favour MMC:

 

  1. Open Competition

Contracts will be restructured to increase SME eligibility by:

  • reducing unnecessary turnover thresholds
  • splitting large bundles into smaller lots
  • standardising tender documentation across local authorities

 

  1. Outcome-Based Weighting

Award criteria will move away from:

  • lowest capital cost
    towards:
  • programme certainty
  • lifecycle cost
  • sustainability
  • repeatable quality

 

These are performance areas where MMC consistently ranks higher.

 

  1. Pre-Approved Design Libraries

Local authorities will tender using pre-certified designs, reducing procurement time and removing bespoke design from the tender stage.

 

  1. Standardised, templated Design & Build procurement

Already tested on 1,500 MMC homes across 36 sites and 13 local authorities.

 

  1. Centralised MMC Data Capture

National Building Control Office now collecting quantitative MMC data for trend tracking, enabling more evidence-based procurement.

 

In effect, the State is removing the procurement friction that has historically penalised MMC and rewarded traditional systems.

 

Rebuilding the Delivery System to Make MMC the Default

Delivering Homes, Building Communities is not another MMC encouragement document. It rewires the building system around industrialised delivery by:

  • mandating MMC through public-sector targets
  • forcing standardisation
  • fixing certification delays
  • funding volumetric systems
  • shifting finance to front-loaded models
  • training a workforce for factories
  • restructuring procurement to reward speed, certainty and sustainability

 

MMC to mitigate the State’s development delivery risk through the following priority actions:

 

🔺Use Modern Methods of Construction in at least 25% of all new social and

affordable homes built during the lifetime of the Plan

 

🔺Increase the use of 3D volumetric systems by providing funding and support for pathfinder projects in Limerick (SMART Homes) and Wexford (3D volumetric units) to create demand for these innovative systems

 

🔺Optimise the process towards NSAI Agrément Certification by promoting the NSAI Agrément Toolkit with industry; and undertaking a root cause analysis to identify constraints on the certification process

 

🔺Scope the potential for the development of an Irish Standard for

Light Gauge Steel

 

🔺Promote opportunities for MMC manufacturers to use ISIF backed funds to

support new and existing factories

 

🔺To meet the growing demand for construction and MMC skills: Renew the Action Plan to Promote Careers in Construction; launch a new 5-year Action Plan for Apprenticeships (2026–2030); and continue to invest in The National Construction Training Campus

 

🔺 Work with partners to deliver on the National Framework for Meeting Priority Construction Workforce Needs

 

🔺Continue to expand MMC training for the construction sector to encourage and support the development of the Small and Medium Enterprise

homebuilder sector, the Land Development Agency will actively seek to engage the sector in the roll out of its LDA Regional programme of work

 

🔺Double overall investment under Enterprise Ireland’s Built to Innovate programme, to drive adoption of efficient construction practices and the use of MMC

 

🔺Introduce a tailored training and mentorship programme on Strategic Financial Leadership for residential construction enterprise supply-chain clients